Loading ...

Blob

Smart Reasoning:

C&E

See more*

Qaagi - Book of Why

Causes

Effects

Identifying factorscreatescope changes

A cultural change document with steps ... the factorscreatescope change

the company ... whose process requirementsdid ... causescope changes

If the project manager wantsto createa scope change

tryingto preventscope changes

seeresultsin scope change

Issuesoften resultin scope change

used by Lexto triggera scope change

not the personcausedthe scope change

new discoveries during the project , external circumstances or internal changes in the business(passive) can be caused byScope change

either field conditions or design changes(passive) caused byscope changes

a requirement for an alert to be triggered that will send an email when any active sprint is added towill causescope change

the pathhas createdthe scope change

Purchaser(passive) caused byScope Changes

the ability of a stakeholderto influencea scope change

to preventtriggeringscope changes

how certain bindingsmay causea scope change

Managing projects with unrealistic deadlines , undefined goals and prioritiescan causescope change

client and contractor personnelcan causescope change

underlying business changeresultsin “ scope change

your entire team ... the firstto discovera scope change

The PM must determinecausedthe scope change

increased user knowledge(passive) caused byscope change

those areas ... most frequentlycausea ‘ scope change

Some situationscan causescope change

the data for the type of instructionscausea scope change

a loss of control of the team‟s planned workcausea loss of control of the team‟s planned work

in alterations to the Projecthas resultedin alterations to the Project

in changes to either the project cost or schedule or bothalmost always resultsin changes to either the project cost or schedule or both

a tradeoff between project requirement and objectivecreatesa tradeoff between project requirement and objective

project performance at KNYS projectsinfluencedproject performance at KNYS projects

contract re - negotiationswill causecontract re - negotiations

significant delayscould have causedsignificant delays

to and require changes to cost , time , quality , or other project objectivesmay leadto and require changes to cost , time , quality , or other project objectives

from changes in designresultingfrom changes in design

large problems with a waterfall project ’s schedule and budgetcauselarge problems with a waterfall project ’s schedule and budget

potential cost / schedule variance(passive) caused bypotential cost / schedule variance

delays or cost overrunsmay causedelays or cost overruns

them to do additional work outside the original agreementleadthem to do additional work outside the original agreement

to project overrun , excess work and claims which eventually increase cost of the projectoften leadto project overrun , excess work and claims which eventually increase cost of the project

to the diversion of the important project resources which against the original plan or those that have not been put as part of the projectleadsto the diversion of the important project resources which against the original plan or those that have not been put as part of the project

in cost overruns and schedule delaysresultin cost overruns and schedule delays

actions related to budget changesmay triggeractions related to budget changes

corresponding changes in schedule and/or budgetcausecorresponding changes in schedule and/or budget

when major changes are introduced after the project 's content and schedule have already been agreed upon that affect the project 's schedule , budget or bothresultwhen major changes are introduced after the project 's content and schedule have already been agreed upon that affect the project 's schedule , budget or both

to a delay in schedule or cost overrunscould leadto a delay in schedule or cost overruns

more missed project deadlines and cost overruns than any other factor short of defining the project requirements incorrectly to begin withcausemore missed project deadlines and cost overruns than any other factor short of defining the project requirements incorrectly to begin with

to changes in contract documents and the related cost enhancements § Ways in which the various parties to the project can exit from the project and avoid the liabilities conferred on them by virtue of the contract documentleadingto changes in contract documents and the related cost enhancements § Ways in which the various parties to the project can exit from the project and avoid the liabilities conferred on them by virtue of the contract document

from a study in 2013 concluding that it would take a multimillion - dollar project ( adding a lane of traffic ) to dramatically decrease congestion ... and such money was not in the budgetresultedfrom a study in 2013 concluding that it would take a multimillion - dollar project ( adding a lane of traffic ) to dramatically decrease congestion ... and such money was not in the budget

time schedule changes , which will , in turn , cause budget changeswill causetime schedule changes , which will , in turn , cause budget changes

in changes in the Division 's ES&H management practicesresultedin changes in the Division 's ES&H management practices

in baseline changes with the ultimate effect of elongating the schedule and driving up the costresultin baseline changes with the ultimate effect of elongating the schedule and driving up the cost

from changes in client needs , discovery of defects or omissions , regulatory changes , etccan resultfrom changes in client needs , discovery of defects or omissions , regulatory changes , etc

to the business objectives approved by the investment council Empowering project team members to say “ no ” to informal change requests that may or may not provide a quantifiable benefit Demonstrating that seemingly great ideas might not stand up to a structured impact analysis Do not spend your valuable time seeking directions to an undetermined destinationwould contributeto the business objectives approved by the investment council Empowering project team members to say “ no ” to informal change requests that may or may not provide a quantifiable benefit Demonstrating that seemingly great ideas might not stand up to a structured impact analysis Do not spend your valuable time seeking directions to an undetermined destination

the contractor to purchase additional supplies and required additional lead time and so the Changes Clause ( 52.243 - 1 Alternate II ) was used for the within scope change and the contractor was granted an extension of 3 monthscausedthe contractor to purchase additional supplies and required additional lead time and so the Changes Clause ( 52.243 - 1 Alternate II ) was used for the within scope change and the contractor was granted an extension of 3 months

from the stake holdersmay originatefrom the stake holders

in performance improvementsmay resultin performance improvements

a code checkshould triggera code check

in new riskscan resultin new risks

to additional costsleadto additional costs

ISSUECreateISSUE

a modification to the Sprint Goalcausesa modification to the Sprint Goal

in additional or omitted workmay resultin additional or omitted work

a negative impactcan causea negative impact

Periodic Payments to applymay causePeriodic Payments to apply

in a need to renegotiate contract terms and conditionsoften resultin a need to renegotiate contract terms and conditions

Blob

Smart Reasoning:

C&E

See more*