by Change Orders(passive) directly caused byPercent change in project duration
resultsleadingto reduced project duration for the customers
Poor Design ... ......................................................................... 137 6.4 Impacts and Mitigation Measures Construction Phaseleadingto Reduced Project Life
interest in the extent to whichcontributeto a reduction in planned project duration
techniquesleadingto radical reduction in project cycle time
t of this approach is enhanced communicationsleadsto minimizing costs and project duration
the best combination of employees and resourcesleadsto a decrease in project duration
employees and resourcesleadsto a decrease in project duration
When uncontrolled changes in the project requirementsleadto longer project duration
all the necessary features in the standard versionledto a short project duration
Because most variations led to activity delaysledto longer project duration
appropriate selection of the resource option for each activity in the projectleadsto the minimum project duration
the hydration of cementcausesreduction in setting time
major application for digital prototyping analysis and simulationleadsto significant reduction in project life cycle duration
in the Project Settings dialog box(passive) is setMaximum project duration
The logical approach ... those activitiescontributeto reduce the project duration
up - to - date Voice Conferencing creates more effective working practicesleadingto reduced project timescales
to identify an optimum crew formation and interruption option for each activity in the projectleadingto minimum project duration
Earlier assessment of work zone impacts Can leadto reduced project
in turncontributedto reduced project
the manual quality assuranceresultingin a significant reduction in project duration
mainly because your metabolism will be more quicklycausinga reduced duration of effect
The failure to pass on early completion and the propensity to multitask ... two factorscontributeto extend the project duration
Cost savingscan resultfrom a compressed project duration
ableto contributeover the project duration
In addition , another characteristic was foundinfluencesProject Duration
factorsinfluencingproject duration
factorsinfluenceproject duration
by : A ) Imposed project deadlines B(passive) caused byproject duration
their abilityto influenceproject duration
Projects(passive) should be designedDuration of Project
from July this year(passive) has been setIts project duration
sources and eventswill contributein project duration
by Change Orders(passive) directly caused byproject duration
by Question(passive) caused byproject duration
by Question 25(passive) caused byproject duration
usually(passive) is ... setProject duration
at two years(passive) is setProject duration
for two years(passive) is setProject duration
significantly moremight contributereduction in responses duration
successful implementation of both modulescausedsuccessful implementation of both modules
normallyresultsnormally
in savings in all aspectsresultingin savings in all aspects
a leading - diploma workto discovera leading - diploma work
to Economic Priority 7contributing substantiallyto Economic Priority 7
in a longer schedule and a decreased scopecan resultin a longer schedule and a decreased scope
module units and installations(passive) are designedmodule units and installations
client expectations and communicating my expertiseam settingclient expectations and communicating my expertise
in higher indirect costswill resultin higher indirect costs
to a successful decrease in the average length of ones casehas ... ledto a successful decrease in the average length of ones case
to escalation of overhead costsleadsto escalation of overhead costs
the solution(passive) was designedthe solution
reduction in indirect costs but increases other direct costscausesreduction in indirect costs but increases other direct costs
in cost savingswill resultin cost savings
in pushing back other projectscan resultin pushing back other projects
to less stress for the patient and reduced costsleadsto less stress for the patient and reduced costs
The C - Bus system(passive) was designedThe C - Bus system
in a lot of frustration and costs on your partcan resultin a lot of frustration and costs on your part
in a total extension of time 36 monthsresultedin a total extension of time 36 months
up to public operationleadingup to public operation
dissemination and exploitation of results and impact and disseminationresultsdissemination and exploitation of results and impact and dissemination
to productionleadingto production
o productionresultso production
to rising obsolescencecontributesto rising obsolescence
dissemination and informationresultsdissemination and information
and built simultaneously in 8 weeksDesignedand built simultaneously in 8 weeks
to disputes and litigationleadingto disputes and litigation
and built simultaneously and completed within 8 weeksDesignedand built simultaneously and completed within 8 weeks
failure of the block to last the duration of surgerycausingfailure of the block to last the duration of surgery
modules for mining production 's modular installations(passive) are designedmodules for mining production 's modular installations
from the use of full road closureresultingfrom the use of full road closure
modular installations(passive) are designedmodular installations
to a fall in the overall caloric intakedoes leadto a fall in the overall caloric intake
from creep of the roperesultingfrom creep of the rope
it to decreasecausesit to decrease
from this shiftresultedfrom this shift
to improvement in safety outcomeswill leadto improvement in safety outcomes